On the 20th of May at 16:11, the reactor of the innovative power unit 6 of Novovoronezh NPP – the first in series of Generation III+ - achieved the minimum controlled power (MCP), said Vladimir Povarov, the Plant Manager.
Thus, the controlled chain fission reaction has started in the reactor, which operates at power which is less than 1% of the rated value; the standard ionizing chambers recorded neutron flux that corresponds to the minimum controlled power.
According to the regulations, during the reactor MCP operation the plant and sectoral specialists will measure actual neutronics of the reactor core to confirm compliance with the design parameters and correctness of functioning of the reactor control and protection systems.
Achievement of the reactor criticality and completion of physical tests at MCP is the final stage of the first criticality program of Unit 6. It was preceded by charging the reactor with nuclear fuel, assembling the reactor, and tests in the subcritical state.
Rostechnadzor confirmed that the power unit was prepared for MCP; the agency controlled the work at each stage of the facility construction.
The next stage that follows the first criticality will be stage-by-stage power build-up, which is accompanied with a large number of tests and measurements. Then, the turbine start from rests (normal spin up when the turbine generator’s rotor running idly) will come, which is most important and critical operation at the stage of the first power. Its idle trials and connection of the generator to the grid will come later. 
Power units of Generation III+ now are built in the USA, France and other countries. Unit 6 of Novovoronezh NPP, however, has become the world’s first nuclear power unit of the latest generation, which is not just built but also reached the first criticality. 
For information:
Unit 6 of Novovoronezh NPP is a generic design of the Russian NPP of the new Generation III+ with advanced technical and economic parameters. It is built to the AES-2006 design with the reactor installation VVER-1200. Its base is the 50-year experience in safe and accident-free operation of NPPs with VVER reactors. The modern design takes account of requirements of the Russian scientific and technical documentation and the IAEA recommendations. The main feature of the innovative power unit is the use of additional passive safety systems in combination with traditional active systems. The new design envisages protection against an earthquake, tsunami, tornado, and aircraft crash. According to the new safety standards, the reactor hall has the double-wall containment; there is a core catcher under the reactor pressure vessel; the power unit is fitted with the passive residual heat removal system. 
JSC Concern Rosenergoatom is the customer for construction of two new generation reactors to the AES-2006 design at Novovoronezh NPP. The Group of Companies ASE is the principal contractor; JSC Atomenergoproekt is the architect general; JSC OKB Gidropress is the general designer of the reactor installation; and NRC Kurchatov Institute is the scientific supervisor.

Source: Information and Public Relations Department of JSC Concern Rosenergoatom, Communications Department of the Group of Companies ASE